From Dispatch to Production in less than two weeks – turnkey 250 kW SOEC Dynamic Electrolyser Unit installed succesfully
July 7, 2026
Five days after dispatch from the assembly facility in Denmark, the unit arrived to Syntholene Energy‘s site at Husavik in Iceland – and less than two weeks after dispatch, the 0.25 MW SOEC Dynamic Electrolyser Unit (DEU) from Dynelectro was integrated with Syntholenes Geothermal heat recovery system and ready for production.
In a likely industry first for a first-of-a-kind technology, Dynelectro‘s 250 kW DEU with our proprietary “Dynamic AC:DC Operation” integrated, was up and running just 10 days after arriving at Syntholene Energy‘s eSAF demonstration facility in Húsavík.
This milestone proves our turnkey alternative to traditional electrolysis — converting up to 90% of electricity into hydrogen — is genuinely field-ready and scalable.
Video is a timelapse of the installation of our turn-key modular electrolyser solution.